Re: Permit Requirement Q

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Lew,

I will fax you section 106.3.4.2 from the 1997 UBC in the morning (weekend 
rates are lower).  I thank you for calling my attention to the fact that the 
IBC 2000 draft has the section entitled "Phased Construction," which in my 
mind's eye is very different from "Deferred Submittals."

It was my understanding that with the 1994 UBC (and SSCBI and BOCA) that the 
sections would be uniformly numbered, so I am surprised that the same section 
of the Southern Building Code would not have similar language.

A. Roger Turk, P.E.(Structural)
Tucson, Arizona