Answer to 3. - The deputy inspector is responsible for ensuring that the water
in the mix does not exceed the maximum allowable water per the concrete mix
design.
Answer to 4. - The maximum slump is specified on the concrete mix design.
(The operator of the concrete pump should not arbitrarily be adding water,
especially if it would result in exceeding the maximum allowable water in the
mix.)
Answer to 5. - An approved mix design and a reputable deputy inspector should
be sufficient.