Re: Problem with Deputy Inspector -- Follow-up

[Subject Prev][Subject Next][Thread Prev][Thread Next]
-----Original Message-----
From: Robert Bill <4robb(--nospam--at)gte.net>
To: seaoc(--nospam--at)seaoc.org <seaoc(--nospam--at)seaoc.org>
Date: Wednesday, April 01, 1998 2:40 PM
Subject: Re: Problem with Deputy Inspector -- Follow-up


>Just out of curiosity--- when you say "because it is not going to be
>placed!!!" Did you physically stand in front of the chute? Lay in the
>footing? or threaten bodily harm?  that's why we have correction notices.
>Robert Bill
>-----Original Message-----
>From: Resengin <Resengin(--nospam--at)aol.com>
>To: seaoc(--nospam--at)seaoc.org <seaoc(--nospam--at)seaoc.org>
>Date: Wednesday, April 01, 1998 12:16 AM
>Subject: Re: Problem with Deputy Inspector -- Follow-up
>
>
>>Re: Slump Test
>>
>>When I took slump test on the job site if the slump wasn't right the
>concrete
>>didn't get placed.  And cylinders were not taken on that batch.  The
>concrete
>>supplier had to figure ot what to do  because it is not going to be
>placed!!!
>>
>>Jay L. Crawford, P.E.
>>
>>
>