Help...what am I doing wrong? I was using the tool to check a 30 x 
30 x12 footing. Each time, the program told me that the 
dimensions were to small due to development length required for #4 
bars.

Can someone tell me what I am doing wrong, because for 4000psi 
concrete, 60000psi uncoated steel, the development length should 
come out at around 19 in.  The bars in my footing are longer than 
this.