Calculation submittals

[Subject Prev][Subject Next][Thread Prev][Thread Next]
"1.6 CONNECTION DESIGN    
      1. Transmit to the engineer, at his request, one copy of the calculations for all of the connections. The responsibility to provide appropriate connections in terms of dimensions, capacities and general layout remains that of the Contractor regardless of any indication to the contrary which may be contained in the afore-mentioned reference standards."
 
 
The preceding was taken from a steel detailing list.  In light of the past weeks discussions concerning the EOR's responsibilities and submission of calculations, I'd be interested in comments concerning this clause taken from someone's steel specs.
 
Scott A. Dunham, PE
Dunham Engineering Services
Dothan, AL