Grouting CMU walls

[Subject Prev][Subject Next][Thread Prev][Thread Next]
I would like to solicit opinions as to how long the
concrete block sub-contractor should wait between
grouting one lift and starting to lay block for the
next lift.  My concern is that if the contractor
starts to lay block too soon, while the grout is
still in its plastic state, cracks could develop due
to workers bumping and hitting the wall (by accident
of course).

I can not find any recommendations in the Code in
this area.  Any opinions, and or any directions to
standards that there may exist would be appreciated.

Thanks

Lynn

******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********