Any suggestions for adding three to four inches of concrete on an existing
slab? The slab has been previously abraded in unsuccessful attempts to
install a topping and there needs to be a new radiant heat system installed
in the new concrete ( a grid of 1 inch pipes, typically attached to any
reinforcement), necessitating a layer of insulation between old and new.
Particular concerns will be crack control and curling.

The reason for the contractor abandoning the topping repair was the poor
quality of the substrate, revealed during scarifying. Replacement of the
slab is not an option.

Thanks in advance.

James Cohen, PE
James Cohen Consulting, PC
Pennington, NJ
http://expertpages.com/jccpc


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********