Re: Building Permit in Monterey County

[Subject Prev][Subject Next][Thread Prev][Thread Next]

Yi,

I was involved recently in the design of a 1000 Megawatt power plant in Monterey County (Moss Landing, CA) and our initial contacts were with the county building official.  Eventually the county completely pulled out of the project (I didn't know they could do that??) and our client ended up hiring a private company to act as the building official (with the OK from the California Energy Commission).  I am not surprised that you are not getting much of a response; neither did I.  At the time (about 2 years ago) they said they were going through a "reorganization" which by the way they said it did not seem too pleasant.  The story I heard was that there was an election and the new elected guy was trying to get rid of the old staff.  From the answers I was getting I do not think the local building official (I think there is only one) had any engineering background; more of an appointed administrator.

Anyway, I would recommend you follow the UBC to the extent you can whether you go for a building permit or not.  There is no reason why a winery should be any less safe than a power plant, 7/11 store, or a donut shop.  It might also help your liability lawsuit if one of those tanks falls over and hurts someone.

Thomas Hunt, S.E.
ABS Consulting



YI <YI(--nospam--at)summit-sr.com>

08/19/2002 05:18 PM
Please respond to seaint

       
        To:        "'seaint(--nospam--at)seaint.org'" <seaint(--nospam--at)seaint.org>
        cc:        
        Subject:        Building Permit in Monterey County



Has anyone done any structural work in Monterey County?
 
I tried to call the building department but I'm getting answers slowly.
 
I have a winery project in the central cost, I wondering if a building permit is required for wine storage tanks (very large tanks, 12'-15' diameter, 20'-25' height) anchorage.  I think the tank foundation needs to have a permit.  What about the anchor designs, since the tanks are not really designed per any code requirement.  Also the catwalk system that's needed to access the top of the tank.  I think these are considered "process equipment" and does not need any building permit.  
 
Any ideas?  Thanks
 
 
Y i   Y a n g  P. E.
Summit Engineering Inc.