RE: Drilled Pier Spacing

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Title: RE: Drilled Pier Spacing

I would think that you ought to be fine with your 12'-14' spacing, but I'd confirm with your geotech.  Typically, the geotech gives us guidelines regarding pier spacing that sound something like this: "With 3 pier diameters clear between piers, use the full allowable soil values (friction and end bearing).  At zero clearance (piers touching), allowable skin friction is zero.  Linearly interpolate for spacings in between."  Obviously, 12' is significantly greater than 3 pier diameters, so it's unlikely you'd have any reduction in pier capacity due to pier spacing.

-- Joel
-------------------------
Joel Adair, PE
Halff Associates, Inc.
E-mail: jadair(--nospam--at)halff.com
-------------------------
 

-----Original Message-----
From: richard lewis [mailto:rlewistx(--nospam--at)juno.com]
Sent: Saturday, November 02, 2002 4:33 PM
To: seaint(--nospam--at)seaint.org
Subject: Drilled Pier Spacing


I am doing a drilled pier foundation with grade beams in expansive soil.
I typically don't do this so I am trying to find out some common design
practices.  Basically I want to know what might be the target spacing of
the drilled piers.  It is commercial construction.  What would be a good
first trial value?  I was thinking of trying to stay in the neighborhood
of 12 - 14 ft. o.c. and use 18" dia piers.  They need to go down about 12
feet into the soil.  Should I be looking at a larger spacing of 18 - 20
feet?  The wall construction is concrete filled foam forms.

The advantage of the shorter spacing is the system is stiffer with less
deflection, lower shear values.  The disadvantage is more drilled piers,
higher deflection and shear values.

Any other suggestions would be appreciated!

Thanks!

Rich


________________________________________________________________

Sign Up for Juno Platinum Internet Access Today

Only $9.95 per month!

Visit www.juno.com

******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********