Fire Rating

[Subject Prev][Subject Next][Thread Prev][Thread Next]
We would like to construct a concrete floor using  UL D920 with 4 1/2" min.
of normal weight concrete above an approved composite metal deck that has 2
hour fire rating with no fireproofing. If the floor is poured with 5" over
the deck, then where we have grout set tile (1 1/2" depression)  we would
have only 3 1/2" of concrete over the metal deck plus 1" of grout as a
setting bed for quarry tile. Would this meet the 2 hour fire rating? We
would not count the quarry tile as contributing to the fire rating.

Jim K.



******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********