Butt-welding a gap

[Subject Prev][Subject Next][Thread Prev][Thread Next]
I am reviewing a welding procedure to "fill-in" a gap for a beam flange
moment connection. The gap is about 2" and it will filled in as a
butt-weld. They are claiming this is a pre-qualified weld (BU-4a-GF),
but I'm not sure that is correct.

I am wondering if some time should be allowed between passes to allow
the weld to cool? I can't find anything in the AWS for this.

(Note the connection is NOT for a seismic application.)

 TIA

******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********