RE: Thickened footings under interior braced walls (Was: RE Hardy Frames)

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Thor,
I couldn't connect to your www.shearwalls.com - I kept getting that the
site could not be found. Is it up and running?
Dennis

-----Original Message-----
From: Thor Matteson, SE [mailto:matteson(--nospam--at)yosemite.net] 
Sent: Sunday, October 26, 2003 6:50 AM
To: SEAINT
Subject: Re: Thickened footings under interior braced walls (Was: RE
Hardy Frames)

Two points to make:

First, in response to Antonio,  the Code People (in particular, John
Henry
of the ICBO/ICC) make a distinction between BRACED walls and SHEAR
walls.
Braced walls occur in Conventional Light-frame construction, and include
let-in braces and gypsum sheathing (shudder).   The conventional framing
section of the code does not mention Shear Walls.  So while any engineer
knows that OF COURSE you need a foundation under a Shear Wall, the code
does
not require them under Braced Walls.

Which brings up point #2:  Section 2320.11.3 requires that "sills shall
be
bolted to the foundation or slab in accordance with Section 1806.6".  It
does not say what thicknes the slab should be.  Section 1806.6 requires
7-inch bolt embedment into concrete (not a combination of concrete and
dirt...)   If you have an "alternate braced wall panel" that requires
tie-downs with the 1800 or 3000 pound capacities, you are not going to
get
the manufacturer's rated uplift capacities by embedding an anchor rod
for
the tie-down into a 3-1/2 inch slab.

I don't see any way that a reasonably responsible building official
could
allow installing a braced wall panel on a slab (or thickened part of the
slab) less than 10 inches thick.   Note the qualifier used before
"building
official".

As for the Conventional Framing section of the code and the IRC, I think
they have their place--but we are seeing huge abuses of them where
designers
are pushing the envelope in every direction possible, all at the same
time.

Thor Matteson, SE

www.shearwalls.com




******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ******** 


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********