Re: Development length in Shotcrete

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Gail:

To my knowledge, you would use the same development / lap lengths as is
specified in ACI 318.  To my knowledge, ACI 318 would by large still
apply.  But I don't have anything at the moment to back this up with other
than my opinion.

And no, none of the other 506 documents appear to address the issue
either.

HTH,

Scott
Adrian, MI


On Tue, 16 Nov 2004 GSKWY(--nospam--at)aol.com wrote:

> When doing a structural wall in shotcrete,  are the development / lap lengths
> typically specified the same as for a poured concrete wall?
>
> ACI 506 does not address this.  Is this addressed in one of the other 506
> documents?
>
> Gail Kelley
>

******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********