"A week or two" sounds like heaven!!  I've had reports of months before even getting a first review from the building department.  Berkeley's promise (as I understand it) of a 3-week turnaround is the best I've seen.  A little one-room addition to a house in a small town near Berkeley CA took 5 months to get approval, with NO complications (like variances)! 

Ralph Hueston Kratz, S.E.
Richmond CA USA

In a message dated 3/9/05 11:14:23 PM, dennis.wish(--nospam--at)verizon.net writes:
Most plan check authorities have at least a week or two (most have more in busy areas) to turn around the plan review and this means that the project goes into the hopper and does not get started for a week or more ...