Roof to top plate connection?

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Hello All--
 
Using the allowable plywood shear capacities for horizontal diaphragms from IBC 2003. The drawings called for full depth blocking at the interface between roof sheathing and top plate. In this case, the contractor left an 1-1/2 air gap between the underside of the sheathing and the blocking. The joists themselves are 2x12. Of course required edge nailing was not achieved. The lateral loads are quite minimal--unblocked diaphragm is more than acceptable.
 
I have always called for full depth blocking in this condition, but now I'm getting some conflicting information, i.e. that since the testing was for an unblocked diaphragm, this condition will still develop the full lateral capacity noted in the IBC table--as long as an alternate method of transfering the lateral load into the top plate is provided. In this case, the "hurricane ties" supply adequate lateral capacity.
 
 
This situation causes me some concern, but I'm being overruled by higher-ups. But then, I wonder if I'm too reliant on academic sources, and not being flexible enough in my thinking.  In the past I've always required additional blocking to "fill the gap", using A34's or A35's  with screws into the underside of the sheathing as necessary to maintain a continuous load path. I'm wondering what the list thinks?
 
Thanks.
 
Paul Skidmore