Well, I certainly wouldn't want to name any names, publicly refer to any vendors, or insult anyone,  but if you call up the article below and scroll down to page five,  you see a drawing of what looks darn-like a multi-strand anchorage.
 
http://www.vsl.net/news/media_coverage/ci2505loper.pdf 
 
And the pictures I have of these anchorages (in-situ as it were) look darn-like the pictures in this article. 
 
I took pictures of this garage only because I had nothing else to do while waiting for the shuttle bus.  I have other pictures (from other structures) from litigations.  The beam anchorages always kind of look big and round,  not little and rectangular.
 
 
Gail Kelley
 
 
 
-----Original Message-----
From: Gil Brock <gil(--nospam--at)raptsoftware.com>
To: seaint(--nospam--at)seaint.org
Sent: Tue, 03 May 2005 09:06:51 +1000
Subject: Re: PT Construction

Gail, 
 
I have never, in 30 years, used multi-strand tendons in anything other than a very heavily loaded transfer member or a bridge. 
 
I have never used one in a parking garage or other normal building member. The jacks used are standard single strand jacks. If the US PT industry uses multi-strand tendons in this type of bonded member, it is no wonder bonded PT has never taken off there as it has in many other areas of the world. 
 
At 12:22 AM 3/05/2005, you wrote: 
 
>Problems with getting the beams stressed has pretty much make grouted PT >construction a non-viable option for parking garages in this >country. The beam tendons in grouted one-way slab and beam construction >are multi-strand tendons which require a special jack. Usually, the >stressing is done by the p-t supplier, and there are always problems with >getting them out to the site in a timely fashion. 

>In other countries, where it is standard construction, grouted PT works >fine. Grouted pt works fine in bridges, too, except the presentations I >have seen on the new cable-stay bridge in Boston were not >confidence-inspiring, as far as the quality of the inspection on >construction of the deck. 

>Gail Kelley 
 
Regards Gil Brock 
Prestressed Concrete Design Consultants Pty. Ltd. (ABN 84 003 163 586) 
5 Cameron Street Beenleigh Qld 4207 Australia 
Ph +61 7 3807 8022 Fax +61 7 3807 8422 
email: gil(--nospam--at)raptsoftware.com 
email: sales(--nospam--at)raptsoftware.com 
email: support(--nospam--at)raptsoftware.com 
webpage: http://www.raptsoftware.com 
 
 
******* ****** ******* ******** ******* ******* ******* *** 
* Read list FAQ at: http://www.seaint.org/list_FAQ.asp 
* * This email was sent to you via Structural Engineers * Association of Southern California (SEAOSC) server. To * subscribe (no fee) or UnSubscribe, please go to: 

* http://www.seaint.org/sealist1.asp 

* Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you * send to the list is public domain and may be re-posted * without your permission. Make sure you visit our web * site at: http://www.seaint.org ******* ****** ****** ****** ******* ****** ****** ********