This is a late response since I was out all last week, but just a note that for DSA and OSHPD projects in California the foundation is also required to be designed for the Omega forces (with a few other possible limiting exceptions).

Thomas Hunt, S.E.
ABS Consulting



"Yi Yang" <YI(--nospam--at)summit-sr.com>

05/31/2005 10:10 AM

Please respond to
<seaint(--nospam--at)seaint.org>

To
<seaint(--nospam--at)seaint.org>
cc
Subject
RE: Braced Frame Anchorage





For OBF, aren't all the connections need to be designed for Omega force?  The foundation doesn't need to be designed for the Omega level reaction, but the I have designed anchor bolts for the Omega forces, including embedment.


Y i   Y a n g,   S. E.            
STRUCTURAL DIVISION
SUMMIT ENGINEERING INC.
707.527.0775.x15
Santa Rosa, California

-----Original Message-----
From: Paul Feather [mailto:pfeather(--nospam--at)SE-Solutions.net]
Sent: Tuesday, May 31, 2005 9:03 AM
To: seaint(--nospam--at)seaint.org
Subject: Re: Braced Frame Anchorage

Tim, you are correct.  The brace must be designed for the amplified force, not the overall frame.

Paul Feather PE, SE
www.SE-Solutions.net
pfeather(--nospam--at)SE-Solutions.net
----- Original Message -----
From: "Tim & Dadre" <stickyfeet(--nospam--at)earthlink.net>
To: <seaint(--nospam--at)seaint.org>
Sent: Tuesday, May 31, 2005 8:38 AM
Subject: Braced Frame Anchorage


> I'm working on a braced frame using the exception in the code for 1 and 2
> story buildings- the code allows any configuration as long as the brace is
> designed to Omega the design force.  The questions is do I then design the
> concrete anchorage to the force without the Omega factor.  I looked at the
> Hardy Frame Info and the simpson steel strong wall and this is what they
> seem to have done.
> Thanks for any insight
> Tim
>
> ******* ****** ******* ******** ******* ******* ******* ***
> *   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
> * *   This email was sent to you via Structural Engineers *   Association
> of Southern California (SEAOSC) server. To *   subscribe (no fee) or
> UnSubscribe, please go to:
> *
> *   http://www.seaint.org/sealist1.asp
> *
> *   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you *   send to
> the list is public domain and may be re-posted *   without your
> permission. Make sure you visit our web *   site at: http://www.seaint.org
> ******* ****** ****** ****** ******* ****** ****** ********



******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
*
*   This email was sent to you via Structural Engineers
*   Association of Southern California (SEAOSC) server. To
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
*   send to the list is public domain and may be re-posted
*   without your permission. Make sure you visit our web
*   site at: http://www.seaint.org
******* ****** ****** ****** ******* ****** ****** ********