RE: Joints in structural floor slab

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Title: Message
Rich, I just finished a 7-story building 84 metres (about 260 ft) long.  Each floor was done in 3 pours over a 2-week period.  So there were construction joints, and you would do well to specify how you want them done, because otherwise the contractor will decide what's easiest for him. 
 
We have shrinkage cracks in the floors.  What I don't understand is how a shrinkage crack can open up on the top and the bottom surfaces at the same time, and still transmit shear and bending across the crack.  But the floors are standing up well, in spite of that.
 
To minimise shrinkage, apart from choosing a good mix design and curing properly, you could consider leaving a strip in the middle of the 180 ft length, to be poured later.  While this sounds like a good idea, it is not so good in practice.  Pouring that strip on the first floor a month later is not easy when the 2nd and 3rd floors have been poured in the meanwhile.  However it can and has been done with a certain degree of success.
 
We used a camber in the floors, and I am very happy about that.  Deflections after 12 months are very acceptable as a result, despite predictions of doom from one particular competitor because of my flat plate design with 8.4 metre spans.  (Why are engineers so free with criticism of their fellows - or is it just a local phenomenon ?  One of my new clients told me yesterday that he has little esteem for engineers because of that.  Some seem to think they can build themselves up by pushing others down.)
 
With only 15 ft spans, camber will not be necessary.
 
 
 

Kevin Below

-----Original Message-----
From: Rich Lewis [mailto:seaint03(--nospam--at)lewisengineering.com]
Sent: 15-Dec-05 20:41
To: seaint(--nospam--at)seaint.org
Subject: Joints in structural floor slab

I am designing structural slab 80 ft. x 180 ft.  It is a suspended slab on drilled piers.  Supports are typically about 15 ft. on center.  I am investigating the need for jointing.  I have a 6 inch slab with #4 top and bottom reinforcing each way.  Since this is a structural slab I don’t see a need for shrinkage joints.  I was wondering what precautions should be taken to minimize shrinkage cracking of the concrete.  Also, would the 180 ft. span be too long for a single pour?  Would a construction joint be recommended?

 

Thanks for any insight

 

Rich

 


--
No virus found in this incoming message.
Checked by AVG Free Edition.
Version: 7.1.371 / Virus Database: 267.14.0/203 - Release Date: 2005-12-15


--
No virus found in this outgoing message.
Checked by AVG Free Edition.
Version: 7.1.371 / Virus Database: 267.14.0/203 - Release Date: 2005-12-15