Re: Perforated shear wall uplift

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Ralph-
There is a discussion of how the anchorage is supposed to work for perforated shear walls in a paper by Philip Line on the AWC website:
 
http://www.awc.org/Publications/papers/WDFPLine.pdf
 
Regards, 
Bill Cain, S.E.
Berkeley CA
 
 
-----Original Message-----
From: Rhkratzse(--nospam--at)aol.com
To: HoodMO(--nospam--at)ci.anchorage.ak.us; seaint(--nospam--at)seaint.org
Sent: Thu, 2 Feb 2006 13:21:13 EST
Subject: Re: Perforated shear wall uplift

In a message dated 2/2/06 10:12:48 AM, HoodMO(--nospam--at)ci.anchorage.ak.us writes:
2003 IBC section 2305.3.7.2.6 indicates that "perforated shear wall
bottom plates at full height sheathing shall be anchored for a uniform
uplift force, t, equal to the unit shear force, v." Where v is the shear
force for which the bottom plate shear transfer has to be designed.

I have no answers, only more questions.  Does this mean that in a shear wall designed to resist 500 plf must have uplift resistance of 500#?  Or if the wall is 10' long it must have uplift resistance of 5,000#?  And if it's 100' long, 50,000#?

Ralph