RE: Traffic Railing post loads

[Subject Prev][Subject Next][Thread Prev][Thread Next]

Thanks Dave,

I picked up on the “longitudinal” thing after reading my old timber bridge design book.  I have a distance to the top of the top railing of 42”, therefore, the “C” value increases my 10 kips to 15 kips.  I hope I’m reading the “C” increase correctly.  Using ACI 318 the pullout of “L” bolts is very low.  I’m hoping using ACI 318 for the embedment design is acceptable though, as it is all I have.

joe

 

Joseph R. Grill, P.E. (Structural)

Shephard - Wesnitzer, Inc.

Civil Engineering and Surveying

P.O. Box 3924

Sedona, AZ  86340

PHONE (928) 282-1061

FAX (928) 282-2058

jgrill(--nospam--at)swiaz.com

 

-----Original Message-----
From: David Smith [mailto:smith1129(--nospam--at)charter.net]
Sent: Tuesday, March 28, 2006 3:08 PM
To: seaint(--nospam--at)seaint.org
Subject: Re: Traffic Railing post loads

 

Joe:

 

The distribution over four posts is for "longitudinal" loads not "transverse".

 

You can distribute the transverse force over a five foot length of concrete barrier wall.

 

The specs are pretty clear on transverse loads.  Don't skimp on the base.  We just had a case where a pickup truck was saved from going off of a bridge by the heavy base anchorage.  As it was, the hooked anchor bolts actually straightened out and almost came completely out of the concrete.

 

Dave Smith

Smith Associates

Gainesville, GA

 

----- Original Message -----

From: Joe Grill

To: seaint

Sent: Tuesday, March 28, 2006 3:01 PM

Subject: Traffic Railing post loads

 

I have just inherited a problem which is to check the post base connection at the post supporting traffic railing.  I’m not a bridge engineer and haven’t looked at this sort of thing for quite some time.  But, none the less it is now my problem.  Anyway, the way I read the ASHTO spec. (our version is 1996) you have to put the 10 kip vehicle load at each post.  My boss suggests that section 2.7.1.3.3 would allow you to distribute 5 kips over 4 posts instead of the 10 kips to one post.  I’m not sure that is what that section is telling me.  Can anyone out there help me out with this?  If that 10 kip load can be distributed then the base connection (designed by others) may be o.k., but if the post has to take the entire 10 kips then the connection is probably not adequate.

 

Thanks,

Joe Grill

 

Joseph R. Grill, P.E. (Structural)

Shephard - Wesnitzer, Inc.

Civil Engineering and Surveying

P.O. Box 3924

Sedona, AZ  86340

PHONE (928) 282-1061

FAX (928) 282-2058

jgrill(--nospam--at)swiaz.com

 

 