RE: Who decides top of concrete level?

[Subject Prev][Subject Next][Thread Prev][Thread Next]
2 nerves as a matter of fact. The first was the engineer's response to Vish.
The second was your defense of him. I have an extremely short fuse when it
comes to dealing with this type of response.

When I started in this business, structures were riveted so I have had a few
years dealing with clowns like this one. I'm just too old to start listening
to excuses.

Dave 

-----Original Message-----
From: Josh Comfort [mailto:jcomfort(--nospam--at)ggbse.com] 
Sent: March 31, 2006 12:10 PM
To: seaint(--nospam--at)seaint.org
Subject: RE: Who decides top of concrete level?

>Being "harsh towards the engineer"??
>
>Give me a break! Many engineers today assume that detailing firms always
put
>enough money in their quotes to draw things the way they think they should
>be and then redraw things the way the EOR finally decides they should be.

I guess I hit a nerve there Dave.  I just don't think it is productive to
write emails talking about someone being incompetent (as the previous poster
labeled the engineer) when we don't know all of the circumstances.  Maybe
the drawings are as complete as the engineer could get them in the time
constraints placed on them by the owner and the information available.  Do
you know all of the circumstances regarding this project?  If you do, please
enlighten the rest of us.  If not, please provide a constructive suggestion
on how to resolve the problem at hand with the information available.


>Drawings that don't have all the information on them are not complete and
>should not be issued until they are. (perfect world scenario).

This sentence and phrase seem to contradict each other.  It's not a perfect
world and sometimes drawings do go out incomplete (either accidentally or
purposefully).  It's obviously best if the drawings do go out perfect every
time, but I don't think it is reasonable to expect this every time on every
project.


>There are many engineering firms that send their drawings out completed.
Get
>with the program!!

If you are alluding to some magical firm that has never had an RFI generated
from any of their drawings, please congratulate them for me (and if it's not
too much trouble ask them how to cure cancer, solve world hunger and bring
about world peace).

Josh




******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ******** 




******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********