RE: Alternate Cold Joint Location

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Does he realize he will have to drill his forms to accommodate the dowels?
 
MB
-----Original Message-----
From: Bill Allen [mailto:T.W.Allen(--nospam--at)cox.net]
Sent: Tuesday, May 22, 2007 2:36 PM
To: seaint(--nospam--at)seaint.org
Subject: Alternate Cold Joint Location

Dear colleagues,

 

A contractor has requested an alternate cold joint location. In the sketch found in the link below:

 

http://www.allendesigns.com/projects/20603/20603AlternateColdJoint.gif

 

Alternate A is the method shown on the approved plans.

 

Alternate B is what the contractor wants to do.

 

The dowels match the slab bars.

 

Should I have a concern about the request?

 

Regards,

 

T. William (Bill) Allen, S.E.

ALLEN DESIGNS

Consulting Structural Engineers
 
V (949) 248-8588 F(949) 209-2509