ACI 530 calls for cleanouts @ 32" max. o.c. with a 3" min. dimension for grout pours over 5'-0" in the execution part of the document.

----- Original Message -----
From: "Doug Mayer"
To: seaint(--nospam--at)seaint.org
Subject: High lift grouting
Date: Fri, 25 May 2007 10:25:20 -0700

List,

 

I have a CMU wall building in Washington (state) being built that has fully grouted walls and reinforcing at 8? o.c. each way.  The contractor wants to do high lift grouting in lieu of the low-lifts, which is fine with me.  However, the topic of cleanouts has become an issue and I?m not sure of the correct answer.  

 

They would like to do cleanouts at 32? o.c., but I know that older codes and the Concrete Masonry Association of California and Nevada specify that cleanouts are to occur at each vertical cell with reinforcing, or continuous special inspection is to be provided.  But, looking at the IBC 2003 and ACI 530-02 ? the codes for this project ? I can?t seem to find any reference or specification for cleanout requirements.  Any ideas?

 

Thanks for the help,

 

Doug Mayer, SE

Structural Engineer

 

TaylorTeter

Partnership

 

 

 



Bart Needham, SE
Principal, nbse associates, inc.
Office 206-780-6822
Office 805-452-8152
Fax    206-780-6683
Fax    208-693-3667
Mobile 206-300-2346

Office locations:
629 State Street #230
Santa Barbara, CA  93101

205 Fairview Lane
Suite 100
Paso Robles, CA  93446

365 Ericksen Ave. NE
Suite 328
Bainbridge Island, WA  98110

Mail and Deliveries:
321 High School Rd. NE
Suite D-3 PMB 216
Bainbridge Island, WA  98110