Jordan,

Thanks again for your response.  I really appreciate it.

I don't understand your description of the angles.  I was thinking of 4
rods, 2 rows and 2 columns.  I would put a vertical angle tying the two
rows together on each side of the anchor bolt group.  This would be easy
to get concrete around.  I hesitate on a horizontal angle because I think
there is too high a potential for a void somewhere.  I may tie the two
vertical angles together with some flat bars.  I would then wrap all of
this in a rebar cage for the pier.

You figured out my pattern for the email address.  Actually, it's been a
while since I had to change addresses.  I think they have done better at
deleting the spam off the server.  I guess it now comes from harvesting
them from the archives.  I occasionally change my email address to prevent
some of the spam.

Rich


> I was thinking the same thing for the rods - make a weldment of the
> anchor rods, an angle (or four) to form an L in the pier, then rebar (or
> A36 rods) welded along the axis of the angle which extend into the
> subslab trench. Now, there are still some moments to deal with, so the
> concrete in the pier isn't really out of the load path completely. But
> that's why we make the big bucks, right?
>
> Jordan
>
> PS - I noticed you're up to serial number 4 on your email. I lost about
> 2 weeks of seaint recently when my previous address became a
> spam-magnet, and I think the server just gave up and deleted almost
> anything coming into that account.
>
> seaint04(--nospam--at)lewisengineering.com wrote:
>> Jordan,
>>
>> Thanks for the response.
>>
>> I looked at my numbers a little more closely this morning and realize my
>> maximum load combination is 88.9 kips horizontal thrust.  The 60 kips
>> was
>> from the roof snow load.  I also have drifted snow load on the worst
>> case
>> frame, plus the dead load.
>>
>> I wasn't thinking of using 40 grade steel reinforcing.  I was
>> considering
>> using A36 rods.  It would be too confusing to try to get 40 grade rebar
>> for the project.  If I limit the stress to 22 ksi I need (4) 1.125 dia
>> rods.  I'm still wondering about an efficient way to get the force out
>> of
>> the anchor bolts and into the rods.  I 'm considering using some angles
>> to
>> 'dead head' the rods in the pier.  I can see I would put a significant
>> cage of rebar around the bolts.  I would detail a concrete tie beam
>> below
>> the floor slab.  I'm still not comfortable with how the force load path
>> travels from the bolts to the tie rods.
>>
>> Rich
>>
>>
>
> ******* ****** ******* ******** ******* ******* ******* ***
> *   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
> *
> *   This email was sent to you via Structural Engineers
> *   Association of Southern California (SEAOSC) server. To
> *   subscribe (no fee) or UnSubscribe, please go to:
> *
> *   http://www.seaint.org/sealist1.asp
> *
> *   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you
> *   send to the list is public domain and may be re-posted
> *   without your permission. Make sure you visit our web
> *   site at: http://www.seaint.org
> ******* ****** ****** ****** ******* ****** ****** ********
>


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********