PIle Cap Connection

[Subject Prev][Subject Next][Thread Prev][Thread Next]
Hello All,

I have a unique situation where the piles could not be driven to it's full length and therefore had to be cut short. The Rebars at the top of the pile that would have been been used to develop the tension from the pile to the pile cap were lost in this process.

My question is can I use the strands that were exposed from the pile to develop the tension into the pile cap? If so, what percentage of 270 ksi can I use for the tension capacity calculation? I would like to avoid drilling into the pile and epoxing rebar. Any thoughts or help would be appreciated.

Thank you so kindly in advance.

Arshad


      

******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********