RE: tilt elevator panels

[Subject Prev][Subject Next][Thread Prev][Thread Next]

The use of a bentonite waterstop (like Volclay Waterstop Rx) would allow you to take the panel down to the pit foundation.

 

D. Matthew Stuart, P.E., S.E., F.ASCE, SECB

Senior Project Manager

Structural Department

Associate

Engineers and Consultants - CMX

200 Route 9

Manalapan, NJ 07726

732-577-9000 (Ext. 308)

908-309-8657 (Cell)

732-298-9441 (Fax)

mstuart(--nospam--at)CMXEngineering.com

 


From: Brian [mailto:bsh117(--nospam--at)yahoo.com]
Sent: Friday, April 17, 2009 6:47 AM
To: seaint(--nospam--at)seaint.org
Subject: re: tilt elevator panels

 

Thanks Andrew,

Typically, I try not to use masonry elevator shaft walls.  I normally would use a concrete wall with a key joint at the base and a dumbbell bituminous water stop.  However, I don't think this detail can apply at the base of a tilt-up wall since it typically sits on a grout bed.  Am I wrong? 

Thanks,
Brian 

 On Sat, 5/16/09, Andrew Kester <akester(--nospam--at)cfl.rr.com> wrote:


From: Andrew Kester <akester(--nospam--at)cfl.rr.com>
Subject: re: tilt elevator panels
To: seaint(--nospam--at)seaint.org
Date: Saturday, May 16, 2009, 10:00 AM

Brian,

Whether you have a CMU, CIP concrete or tilt elevator wall, you need a good waterproofing detail from your architect. But they put sump pits in elevator pits for a reason...

 

I don't see any structural reasons you couldn't do it either way, but you will want to be careful if you go with a CIP/CMU wall first for the pit, then tilt above that, as you have created a hinge point at the ground floor slab. There are a number of ways to address that in your detailing.

 

If there is a GC on board or you have a relationship with a tilt contractor, you may want to give them a call. I could see them wanting to do the CIP/CMU wall method for ease of work flow, especially with casting the panels. It depends on where they are casting the panels (the interior slab will not be finished or even placed while the pit is being constructed), and how they want to schedule it all. They may want the pit and slab all done prior to doing any tilt panels.

 

Andrew Kester, P.E.
Orlando, FL