My experience is the same, I am not aware of any practice of using only solid-grouted walls, other than for the earth-retaining or fire-rated purposes.
 
V. Steve Gordin, SE
Irvine CA
 
----- Original Message -----
From: Bill Allen
Sent: Sunday, April 26, 2009 12:47
Subject: RE: CMU California Practice in the 1950's

Really?

 

I know the preference for open end blocks which means grouted cells are really grouted double cells, but I'm curious if this is true.

 

After all, grouting solid is a heavier wall producing more force at the tie at the top and increasing the load on the diaphragm. If bars are only required at 48" (#4 @ 24" or even #5 @ 32"), that means half the wall can be un-grouted providing quite a bit of reduction in mass transferred to the roof diaphragm.

 

I've designed quite a few block walls grouted at steel only, all of them since 1980. I'm wondering if I'm out of step with standard practice. Of course, it wouldn't be the first time.

 

T. William (Bill) Allen, S.E.

ALLEN DESIGNS

Consulting Structural Engineers
 
V (949) 248-8588 ? F(949) 209-2509


I know that it has been the general practice in
California to grout CMU walls solid since at least the 1980's. 


Regards, Harold Sprague