Re: Dallas Cowboys Roof Collapse

[Subject Prev][Subject Next][Thread Prev][Thread Next]
I think that the second last two paragraphs tell a tale that really needs to
be addressed in the Arch/Eng/Building Official intersect.

"Construction ended about six months ago on another Summit project in the
state, an athletic complex at Texas A&M. Summit manufactured materials for
that facility and designed it, university spokesman Jason Cook said.

But Cook said Summit did not handle construction or supply the engineer of
record." - Dallas Morning News

Bold generalization: Pre-engineered manufacturers do NOT provide engineering
consulting services and CANNOT act as AOR/EOR for a project - despite the
presence of a properly sealed set of "erection drawings" from the
manufacturer. If the Owner/GC buys pre-engineered "buildings" through a
dealer/broker, the Owner/GC must provide project engineering or
architectural support for their design/build supply scope. The Building
Authority rarely understands this nuance of authority/liability and
frequently assumes that the other professional designers on the project ARE
the AOR/EOR for the pre-engineered scope. Foundation design engineers are
usually the only other EOR involved with the "building" and are frequently
assumed to be accepting responsibility for the pre-engineered structure.

At the Phoenix NASCC I noted that there are more companies now offering more
pre-manufactured structural and secondary structural "systems" than ever
before. This is cost efficient for the owner, but they can't simply assign a
contractor who can point to engineered elements available off-the-shelf and
assemble a building that can be permitted on the basis that every set of
drawings has a seal by a licensed engineer employed by the manufacturer.

Oooh, I could rant on.

Disclosure: I am a member of a Technical Committee of a Canadian national
quality standard that includes metal framed, fabric covered buildings in the
scope of what are traditionally known as pre-engineered metal buildings.
Manufacturer Certification is mandatory within the scope of the building
codes but it does not address the professional responsibility trail at the
permit office. I am addressing that issue by other means.

Regards
Paul
-- 
Paul Ransom, P.Eng.
ph 905 639-9628
fax 905 639-3866
ad026(--nospam--at)hwcn.org



> Subject: Re: Dallas Cowboys Roof Collapse
> From: Stan Caldwell <stancaldwell(--nospam--at)gmail.com>
> To: seaint(--nospam--at)seaint.org
> 
> --001485f7cb5895a9220469661bdb
> Content-Type: text/plain; charset=windows-1252
> Content-Transfer-Encoding: quoted-printable
> 
> Gary:
> 
> Here is the latest newspaper article:
> 
> http://www.dallasnews.com/sharedcontent/dws/dn/latestnews/stories/050809dnm=
> etcowboyscollapse.4057b52.html
> 
> Regards,
> 
> Stan


******* ****** ******* ******** ******* ******* ******* ***
*   Read list FAQ at: http://www.seaint.org/list_FAQ.asp
* 
*   This email was sent to you via Structural Engineers 
*   Association of Southern California (SEAOSC) server. To 
*   subscribe (no fee) or UnSubscribe, please go to:
*
*   http://www.seaint.org/sealist1.asp
*
*   Questions to seaint-ad(--nospam--at)seaint.org. Remember, any email you 
*   send to the list is public domain and may be re-posted 
*   without your permission. Make sure you visit our web 
*   site at: http://www.seaint.org 
******* ****** ****** ****** ******* ****** ****** ********